Two of the three Indigenous-led environmental assessments of the access roads to the Ring of Fire are nearly complete, but the third is expected to take three more years, followed by a decade of construction
Despite the Progressive Conservative government’s promises to fast-track the building of roads to the proposed Ring of Fire mining development in northwestern Ontario as a way to build “Fortress Am-Can” with the United States, current estimates suggest the final leg of the all-season road to the project site won’t be completed until sometime between 2035 and 2040.
At the same time, significant progress is being made on all three access roads needed to connect the Ring of Fire, Marten Falls First Nation and Webequie First Nation with the TransCanada Highway.