The ‘line that brings light’ connects Kingfisher Lake First Nation to the provincial power grid
FORT WILLIAM FIRST NATION, Ontario, Nov. 24, 2022 (GLOBE NEWSWIRE) — Wataynikaneyap Power announces the energization of Kingfisher Lake First Nation, a remote northern Ontario community, which was connected to the provincial power grid on November 8, 2022. Upon grid connection and onto a reliable power source, the community turned off its diesel generators which had previously provided primary power to this remote community.
The Wataynikaneyap Power transmission system connects the Kingfisher Lake community distribution system to the Ontario grid through a total of 250 km of line and two substations, originating from its Pickle Lake Substation. Kingfisher Lake will continue to be served by Hydro One Remotes Communities Inc. (HORCI) for the local distribution of electricity.